Pull up a chair and let me walk you through something that catches out nearly every new account manager who closes a fixed-price project. You will sit in the sales review, someone will say “twenty per cent margin, good deal”, and everyone will nod. Nobody will ask when the money actually reaches the bank. You should ask.

Take a small example. A Vadodara manufacturer hires your company to build a dealer-ordering portal for ₹60 lakh, fixed price, six months. Your delivery cost is ₹8 lakh a month: salaries, a bit of cloud, a bit of management time. Over six months that is ₹48 lakh, so the project earns ₹12 lakh, which is the twenty per cent everyone applauded.

Costs are monthly, cash is lumpy

Your costs behave like a tap: ₹8 lakh flows out every month, because salaries do not wait for a customer’s sign-off. Revenue behaves like a bucket tipped over four times. The contract says so:

  1. 10% (₹6 lakh) on signing.
  2. 30% (₹18 lakh) when the design is signed off at the end of month 2.
  3. 40% (₹24 lakh) when user acceptance testing is passed at the end of month 5.
  4. 20% (₹12 lakh) at go-live in month 6.

Now add the thing people forget: payment terms. If the customer pays 45 days after invoice, each milestone lands about a month and a half after you earn it. I ran this timeline through a small spreadsheet-style calculation. The advance arrives in the first few weeks. Then you spend ₹8 lakh a month and nothing comes in until about the middle of month 4, when the design milestone is finally paid. By that point you are ₹18 lakh down, and the ₹18 lakh brings you back to zero. Then months 4, 5 and 6 are spent again with nothing arriving, until the big acceptance payment lands in the middle of month 7. Just before it arrives, the project has consumed ₹24 lakh of your own cash.

So a project that will eventually make ₹12 lakh needs you to fund ₹24 lakh at its worst point. Your margin is half the size of your funding need. A company that signs several such projects in the same quarter can run short of cash while every single project is profitable. Nobody did anything wrong. The milestone design did it.

Where the funding gap comes from

Three things widen the gap, and you can influence each one.

First, back-loading. The more of the price sits at acceptance and go-live, the longer you finance the project. In our example 60% of the money arrives only after month 5. Customers like back-loaded plans because they feel safe: they pay for results. Delivery teams dislike them for the same reason.

Second, milestones that depend on the customer. “Payable on UAT sign-off” means your cash is hostage to how quickly their business users test. If their testers are busy with month-end closing, your acceptance milestone drifts by three weeks and so does your cash. A good contract defines deemed acceptance: if the customer does not report defects within, say, ten working days of delivery, the milestone is treated as accepted.

Third, payment terms stacked on top. A 45-day or 60-day credit period is invisible in the project plan but very visible in the bank balance. We will not go into the arithmetic of it here; just remember that every milestone has two dates, the date you earn it and the date you collect it, and only the second one pays salaries.

Designing a plan you can live with

When you negotiate, your aim is to make the cumulative cash curve as close to the cumulative cost curve as possible. A few levers, in the order I would try them.

  • A larger advance. Customers often accept 20% if you explain it as mobilisation: you are reserving a team. Some will insist on a bank guarantee against it, which costs you a fee but is still cheaper than funding the gap.
  • More, smaller milestones. Six payments of about 15% each, tied to things the team genuinely delivers (a working module, a completed integration), mean you are never more than a few weeks ahead of the customer’s cash.
  • Time-based instalments for the long middle. If the work is a steady build, monthly invoices against progress can be fairer than three big milestones, and the customer still holds a retention for the end.
  • Retention with a date. Many Indian buyers keep 5% to 10% until the warranty period ends. Accept it, but fix the release date in the contract rather than “after final acceptance”.

Notice what you are not doing. You are not asking for more money. You are asking for the same ₹60 lakh on a different calendar. Customers’ finance teams are usually more flexible about that than about price, because the total they report to their board does not change.

What a sales person should do with this

You do not have to build the cash model yourself, though a ten-line table is not hard. Ask finance for the peak funding requirement of any fixed-price deal above a size your company chooses, perhaps ₹25 lakh. If the peak is larger than the expected profit, as it was here, treat the milestone schedule as a pricing question. One reasonable internal rule is to charge for the financing: if the cost of funding ₹24 lakh for a few months at your borrowing rate is ₹1 lakh or so, that belongs in the margin conversation before you sign, not after.

One more warning. If the scope changes mid-project, the milestones usually do not move with it, so the plan above can get worse without anyone touching the price. Tie change requests to their own invoices.

Finally, a gentle caution about all this: a customer with real cash problems is a bigger risk than any milestone schedule. If a buyer has a history of paying late, shorter milestones help you stop work sooner when payment slips. That is a legitimate reason to ask for them, and an honest one to give.

Figures and names in the examples are illustrative.