In July, Imran Qureshi, who runs a customer support process in Lucknow for a home-appliances e-commerce brand, gets the client’s festive forecast. Normal volume is about 8,000 contacts a day. For the ten days around Diwali, the client expects 2.2 times that, 17,600 a day. Average handle time is six minutes. Imran has about 168 agents today. His question is not “can we cope?” but “how many people do we need to have trained, on the floor, by the first day of the peak, and when do I have to start?”
Step one: turn the forecast into agents
He assumes an agent works an eight-hour shift, loses 30 per cent of it to shrinkage (breaks, training, leave, meetings), and can be kept busy 85 per cent of the remaining time. That leaves 8 x 0.70 x 0.85 = 4.76 handling hours per agent per day.
Normal day: 8,000 contacts x 6 minutes is 800 hours, so 800 / 4.76 is 168 agents. Peak day: 17,600 x 6 minutes is 1,760 hours, so 1,760 / 4.76 is about 370 agents. The gap is roughly 202 agents. That is the base figure, before anything goes wrong.
Two caveats Imran writes in the margin. Festive contacts are not like normal ones: more order-tracking and delivery-delay calls, perhaps a different handle time. And customers who wait in a long queue call again, so volume can overshoot the forecast. He keeps a small buffer.
Step two: allow for people who do not make it
The 202 are the ones who must be productive on day one of the peak. Not all who are hired will be. Suppose he expects 15 per cent to leave or fail during training and nesting. To end with 202 he must start training about 202 / 0.85 = 238 people. And if, historically, about three in ten candidates who accept an offer do not turn up on the joining day, he needs around 238 / 0.70 = 340 accepted offers. (Both are illustrative; his own history is what counts.) So a gap of 202 on paper becomes 340 offers in practice. Forgetting this chain is the commonest way seasonal plans fall short.
Step three: work the calendar backwards
Imran counts back from the first peak day. Nesting, the supervised phase where new agents take live calls with a mentor nearby, runs about two weeks. Classroom training for this process is about three weeks, with product and system modules. Recruitment, from advert to joining, takes three to four weeks with walk-in drives and a recruiter partner. Add a week for system access, seats, laptops and badges. Adding it up, hiring must start roughly nine to ten weeks before the peak. If the forecast arrives in July for an October peak, there is enough time, but not much. If it arrives four weeks out, the honest answer to the client is that a full ramp cannot be done and the plan needs other levers.
Other levers beside hiring
- Freeze planned leave for the peak window, with notice and fair compensation or time off afterwards.
- Cross-train staff from slower processes in the same centre, if the client’s data rules allow it.
- Extend shifts through overtime within the limits of labour law and the centre’s own policy, for a short period only.
- Remove avoidable contacts: proactive delay messages, a clearer tracking page, a simple IVR message about known issues.
- Add self-service options or a callback, as discussed elsewhere on this site, for routine questions.
Seasonal agents are usually simpler-process agents: fewer call types, tighter scripts, escalation to a core team for anything unusual. That is why the knowledge base and the scripts for the peak need to be rewritten for people with three weeks of training, not three years.
After the peak
Seasonal hiring creates a second problem: what to do on day eleven. Contract duration, notice terms and what the client will pay for must be agreed beforehand; ask HR to review how fixed-term hiring should be documented under applicable labour rules. The commercial side matters too. If the client pays only for the peak days but you carry a month of training and nesting costs, the seasonal programme loses money unless it is priced in. Imran’s cost note to the client lists recruitment, training, nesting and the unbilled learning-curve weeks as separate lines.
Some of the temporary staff will be good. A proper conversion path for the best 10 or 15 per cent into permanent roles is cheaper than starting recruitment from zero next year.
Whatever the final headcount, Imran sends the client a one-page plan in July: the forecast he used, the assumptions, the hiring dates and the date after which hiring can no longer help. That last date is the one that protects both sides.
Figures and names in the examples are illustrative.